The conversion depended on AHV, Networking and Uhura, each with its own priorities. The customer timeline was fixed, and $10–20M was at risk if it slipped.
Defeated by a shared mandateDec 2024Slot 02 · Nutanix · Dec 2024 – Oct 2025 · Technical lead
Keeping customers through VMware’s licensing shake-up
VMware’s new licensing forced about 2,000 enterprise customers running Nutanix on VMware to pick one full stack. I led Nutanix Move’s in-place ESXi-to-AHV conversion across three teams, built for zero downtime and shipped on time. About half of those customers stayed with Nutanix.
StageClearOn time
Coloured cubes are the customer’s workloads: they never change.Grey is ESXiindigo is AHV
Results
of affected customers stayed with Nutanix
enterprise customers on Nutanix + VMware
if the release slipped
shipped Sep–Oct 2025
shorter after fixing the QA bottleneck
Mission
The problem
Many Nutanix customers ran a mixed stack: Nutanix software on top of VMware’s ESXi hypervisor. After Broadcom acquired VMware, it changed the licensing so customers had to buy the complete package. Partial subscriptions were gone.
That left about 2,000 enterprise customers with a choice: go all-in on VMware, or move fully to Nutanix. With the new pricing, many wanted to stay with Nutanix. The blocker was the move itself: switching every workload from ESXi to Nutanix’s own hypervisor, AHV, without downtime.
Nutanix needed a product that made that switch seamless, and needed it before customers made their decision.
Boss fights
The hardest parts
Every release queued behind QA. With bugs landing on both our side and the AHV team’s, the date was at risk.
+15% QA capacityCycles ~20% shorterParty
Getting three teams behind one plan
- SponsorsDirectors and VPsBacked the project: 2,000 enterprise customers to retain
- LeadMe, with the Move teamOne plan, one timeline, one voice to customers
- AHVThe core hypervisor and the data path workloads land on NetworkingBrings networks up and down once systems are converted UhuraNutanix running on VMware: where every customer started
- For~2,000 enterprise customersRunning Nutanix on VMware ESXi
Same split as the files migration: Move orchestrates the conversion and gives the user control; the AHV team owns the data path. That meant both teams fixing their own bugs, in parallel, against one date.
Upgrades picked
What I did
- DecisionGot leadership buy-in first
Directors and VPs endorsed the project on one number: 2,000 enterprise customers we wanted to keep.
- DecisionLet customers set the requirements
Heard their migration worries, then pinned down exactly what they needed and which trade-offs they would accept.
- ProcessBriefed all three teams up front
Explained the impact on retention, shared the leadership mandate, and asked for every objection early.
- ProcessBuilt a common base, then split the work
Agreed one foundation across teams, then divided execution into parts each team could own.
- DeliveryBeta in 2–3 months
From the customer’s ask to a working beta, refined from their feedback before release.
- DeliveryWidened the bottleneck
Added two contractors and two test clusters, about 15% more QA capacity. Delivery cycles got about 20% shorter.
Run map
How the release ran
- TriggerVMware licensing change: full stack or leave
- Room 1Director and VP buy-in
- Room 2Customer requirements
- Room 3Brief AHV, Networking and Uhura
- Room 4Common base, work split
- Room 5Beta and customer feedback
- Room 6 · BossQA and joint bug fixing
- ShippedOn time
Dec 2024 · kickoffSep–Oct 2025 · released
Team and loadout
Team and tech
- Me · technical leadAlignment, planning, customer requirements, delivery
- Move team2 backend, 1 UI, 1 UX, 1 product manager, 2 QA
- QA contractorsAdded with two test clusters to clear the bottleneck
- AHV, Networking, UhuraPartner teams across Nutanix
- ESXiVMware hypervisor, the start
- AHVNutanix hypervisor, the goal
- In-placeSame hardware, no new cluster
- SeedInitial copy of each VM
- ΔIncremental delta syncs
- APIAHV data-path APIs
Move orchestrates; AHV moves the data. Workloads keep running until cutover, so the switch is built for zero downtime.
Replay
See the feature
Nutanix University’s walkthrough of the feature in Move 6.1. Nothing loads from YouTube until you press play.
Achievements unlocked
Highlights
- Half the base kept~50% of affected customers stayed with Nutanix
- Three teams, one releaseAHV, Networking and Uhura on one date
- Bottleneck found: QA15% more capacity, ~20% shorter cycles